Project Overview
Overview
Works delivered within the Brisbane Airport precinct involved the investigation and remediation of a failed expansion joint system on a road access bridge, replaced with a durable, heavy-duty expansion joint system suited to sustained traffic loading, together with waterproofing to protect the structure from water ingress.
The Challenge
Challenge
The works were undertaken within a heavily trafficked airport road environment affected by international passenger movements, taxis and general vehicle traffic, requiring high-level traffic management, careful staging and strict public-safety controls while maintaining operational access.
Project Facts
| Location | Brisbane Airport, Queensland |
|---|---|
| Completion | 2024 |
| Approx. Value | Approx. $200,000 |
| Category | Civil • Structural Remediation |
SHENERGY Approach
Approach
SHENERGY carried out a site survey and condition inspection of the failed joint system, developed a suitable remediation design, and coordinated traffic management to allow safe removal and replacement while keeping the bridge operational for surrounding traffic. Waterproofing was applied around the new joint system to protect the structure from ongoing water ingress and support the durability of the repair.
Scope of Works
Scope
- Site survey and condition inspection
- Investigation of the failed expansion joint system
- Development of a suitable remediation solution
- Removal of failed joint components
- Installation of a durable, heavy-duty expansion joint system
- Waterproofing
- Traffic management coordination
- Construction delivery within a live airport road environment
Result
Outcome
The remediated expansion joint system was installed to restore durability and performance under heavy traffic loading, with waterproofing to help protect the structure from water ingress, delivered with traffic management and staging appropriate to a live airport road environment. Works were delivered within the Brisbane Airport precinct.